Transaction Type

Acquisition, Financial Structuring, Funding & Development of a 999 bed new-build PBSA Asset

Investment Category

Equity

Key Risks

Construction, Operation, Occupier Market, Investment Market

Blacklight Value Add
  1. Highly structured ‘rescue’ strategy to acquire asset from administration alongside c.400 private investors
  2. Restructure from fractional ownership to corporate ownership model with Blacklight performing Developer role
  3. Appointment of main contractor under fixed price D&B contract
  4. Tender and appointment of PBSA operator
  5. Third party senior finance raise
  6. Exit of operating asset to institutional ownership
Acquired

September 2020

Status

Development completed and asset fully operational.  Exited to a institutional investors in September 2022

The very early-stage part-constructed site was acquired from administration after Blacklight was able to structure a corporate buyout SPV around a body of c.400 long leaseholder creditors in a failed ‘fractional ownership’ development, in a first-of-its-kind transaction in the UK.  Blacklight was able to convince the Administrator that the SPV it had created was a credible corporate buyer (as opposed to the previous fractional ownership ‘room-by-room’ ownership structure) that had the single point of control and therefore the capability to complete the development in the best interests of the majority of creditors of the administration.  The strategy involved bringing investors together under a corporate umbrella that could then acquire, and offer as security, the asset and the freehold of the land on which it is situated, with Blacklight controlling the development as well as the financing behind the SPV.

The project was completed after the original main contractor, whose contract was renegotiated with all warranties maintained or increased, was brought back on board by Blacklight acting as Developer.  A specialist PBSA operator (True Student) was selected to operate the asset post-completion of construction.  Senior debt was raised to part-fund the construction programme, which completed in two phases, opening 12 months apart as they reached PC.

The scheme was sold for £110,000,000 to a well-known European PE fund into one of its Core+ funds at a record-breaking price per bed for the Liverpool market, proving the quality and specification on the asset as being institutionally-desirable, something that Blacklight had set out to achieve from the start.  The scheme was 100% occupied with a waiting list at the point of sale.

This is a prime example of Blacklight’s ability to turn around a complex failed scheme – in this case investors were facing a 15% recovery from administration proceeds, but ultimately received a c.1.8x  multiple on their equity investment.

Blacklight was shortlisted for Property Week’s Student Accommodation ‘Developer of the Year’ 2022 as a result of delivering this asset.